I can’t for the life of me remember how to copy a scorecard or elements of a scorecard between organisations.  i’m sure I have done it before!

 
  • Liked by
Reply
1 on July 27, 2016

Copying between organisation is easy:

  • Select the object you want to copy in the tree
  • Right click on the object and select copy
  • Go to the organisation where you want to make the copy
  • Select the object you want the copy to appear under
  • Right click on that object and select paste
  • The object (structure) will appear (together with any sub-structure)

The only anomaly to the above is if you copy a complete scorecard and want to paste it straight into a new organisation node. In that instance when you select the new (empty) node, a ‘Paste Balanced Scorecard’ button will appear, just click on that and the scorecard will be copied.